Question: You are managing a software project with an initial budget estimate of PKR 2 million. During interim cost and schedule performance analysis, you figured out
You are managing a software project with an initial budget estimate of PKR 2 million. During interim cost and schedule performance analysis, you figured out that you should have spent $500.000 till now based on your initial plans of schedule activities. Whereas you have spent $600.000 till now of schedule activities which should have cost $450.000 based on your initial plans. On the basis of given information evaluate the progress of your project.Multi Line Text.