Question: You are managing a software project with an initial budget estimate of 5 million USD. During interim cost and schedule performance analysis, you figured out
You are managing a software project with an initial budget estimate of 5 million USD. During interim cost and schedule performance analysis, you figured out that:
- You should have spent $650,000 till now based on your initial plans and 1,500 man/days of scheduled activities
- You spent $425,000 till now and completed 600 man/days of scheduled activities which should have cost $525,000 based on your initial plans.
- You re-estimated the budget required for the remaining work to be done as $4,500,000.
Identify:
- BAC
- PV
- AC
- EV
- ETC
Calculate:
- CPI
- SPI
- CV
- SV
- VAC
- EAC
- TCPI
Once you've calculated this, what does it mean for your project and your stakeholders?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
