Question: You are preparing your monthly status report for your project. Assuming the variances to date are not unusual, what would the ETC (estimate to complete)
You are preparing your monthly status report for your project. Assuming the variances to date are not unusual, what would the ETC (estimate to complete) be assuming your project was budgeted to cost $125,000 and take 12 months to complete and you have actually spent $42,000, produced $37,500 worth of the product and were scheduled to have spent $39,000?