Question: You are the project manager assigned to a project early in the project lifecycle. One of the things that must be done is to do

You are the project manager assigned to a project early in the project lifecycle. One of the things that must be done is to do a justification for the project. Since very little information is known about the project, the estimates are considered to be rough estimates. The following table is the project managers estimate of the cash flow that will take place over the next five years.

End

of Year

Cash Flow In

Cash Flow Out

1

0

15,000

2

15,000

20,000

3

20,000

15,000

4

30,000

10,000

5

45,000

5,000

  1. What is the payback period for this project?
  2. What is the net cash flow at the end of five years?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!