Question: You are working on your network diagram. Activity A is a predecessor to Activity B . Activity B cannot begin until Activity A is completed.
You are working on your network diagram. Activity is a predecessor to Activity Activity cannot begin until Activity is completed. What is this telling you?
A Activity A and Activity are both on the critical path.
B Activity is a successor to multiple tasks.
C There is a mandatory dependency between Activity A and Activity B
D There is a finishtostart dependency relationship between Activity A and Activity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
