Question: You are working on your network diagram. Activity A is a predecessor to Activity B . Activity B cannot begin until Activity A is completed.

You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?
A Activity A and Activity B are both on the critical path.
B Activity B is a successor to multiple tasks.
C There is a mandatory dependency between Activity A and Activity B.
D There is a finish-to-start dependency relationship between Activity A and Activity B.