Question: You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What

You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?

A. There is a mandatory dependency between Activity A and Activity B.

B. There is a finish‐to‐start dependency relationship between Activity A and Activity B.

C. Activity A and Activity B are both on the critical path.

D. Activity B is a successor to multiple tasks.