Question: You complete your PERT calculations for your project and you have determined your expected finish is 168.3 days with a standard deviation of 3.21. What

You complete your PERT calculations for your project and you have determined your expected finish is 168.3 days with a standard deviation of 3.21. What is the Z score for the project completing in less than 173.8 days