Question: You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0 The project's deliverables have
You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0
| The project's deliverables have all been finished. The project came in ahead of schedule but on budget. | ||
| The project's deliverables have all been finished. The project came in on schedule but over budget. | ||
| The project has been canceled while it was executed. At that time the project was behind schedule and on budget. | ||
| The project's deliverables have all been finished. The project came in behind schedule but on budget. |
Option C is incorrect but what I came up with?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
