Question: You have arrived at the optimal solution using Time - Cost CPM Scheduling model analysis. When it had happened? Multiple Choice You no longer have
You have arrived at the optimal solution using TimeCost CPM Scheduling model analysis. When it had happened?
Multiple Choice
You no longer have a linear relationship with costs.
You have reached the minimum total cost.
You have run out of crash costs.
You have run out of crash time.
You have found the critical path.