Question: You know when you have arrived at the optimal solution in using the Time - Cost CPM scheduling model analysis when what happens? Question 7

You know when you have arrived at the optimal solution in using the Time-Cost CPM scheduling model analysis when what happens?
Question 7 options:
a)
You have found the critical path
b)
You have run out of crash costs
c)
You have run out of crash time
d)
You have reached the minimum total cost