You know when you have arrived at the optimal solution in using the time-cost CPM scheduling model analysis when what happens?
Multiple Choice
-
You no longer have a linear relationship with costs.
-
You have run out of crash time.
-
You have reached the minimum total cost.
-
You have found the critical path.
-
You have run out of crash costs.