Question: You have arrived at the optimal solution using Time - Cost CPM Scheduling model analysis. When it had happened? aYou have found the critical path.

You have arrived at the optimal solution using Time-Cost CPM Scheduling model analysis. When it had happened? aYou have found the critical path. bYou have run out of crash time. cYou no longer have a linear relationship with costs. dYou have reached the minimum total cost. eYou have run out of crash costs.