Question: You have been appointed project manager for the project whose activities, predecessors and duration are shown in the table below. You have been informed that

You have been appointed project manager for the project whose activities, predecessors and duration are shown in the table below. You have been informed that the project team will work a standard working week (5 working days per week) and that all activities will start as soon as possible.
(a) What is the planned duration of the project in weeks? Answer 1 Question 6
(b) Complete the schedule in days for each individual activity in the list below.
Activity ES LF Slack
A Answer 2 Question 6
Answer 3 Question 6
Time
Answer 4 Question 6
B Answer 5 Question 6
Answer 6 Question 6
Answer 7 Question 6
C Answer 8 Question 6
Answer 9 Question 6
Answer 10 Question 6
D Answer 11 Question 6
Answer 12 Question 6
Answer 13 Question 6
E Answer 14 Question 6
Answer 15 Question 6
Answer 16 Question 6
F Answer 17 Question 6
Answer 18 Question 6
Answer 19 Question 6
G Answer 20 Question 6
Answer 21 Question 6
Answer 22 Question 6
H Answer 23 Question 6
Answer 24 Question 6
Answer 25 Question 6
I Answer 26 Question 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!