Question: You have been tasked with the following step activities from A to J: Activity Duration (days) Dependency Float Start 0 None A 5 Start B
You have been tasked with the following step activities from A to J:
| Activity | Duration (days) | Dependency | Float |
| Start | 0 | None | |
| A | 5 | Start | |
| B | 2 | Start | |
| C | 3 | A, B | |
| D | 5 | Start | |
| E | 6 | Start | |
| F | 4 | D, E | |
| G | 2 | C, F | |
| H | 5 | G | |
| I | 7 | G | |
| J | 3 | H | |
| End | 0 | I, J |
Draw network diagram. List the network paths and the critical path and expected duration.
Perform backward and forward pass.
Determine float for each activity.