Question: Exercise 4) Activity Duration (Days) Dependency Float Start 0 A Start B Start C Start D A B O - N N - OO -

Exercise 4) Activity Duration (Days) Dependency Float Start 0 A Start B Start C Start D A B O - N N - OO - UI - + F B. C G D H F I G End E, H. I Draw the network diagram 2) List the network paths 3) Perform a forward pass and a backward pass 4) Determine the critical path(s) 5) Determine the float for each activity and for each path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts