Question: You have collected EV, AC, and PV data from your project for a five-month period. Complete the table. Calculate SPIC and CPIC. Compare the cost
You have collected EV, AC, and PV data from your project for a five-month period. Complete the table. Calculate SPIC and CPIC. Compare the cost and schedule performance for the project on a month- by-month basis and cumulatively. How would you assess the performance of the project? (All values are in thousands $.)
|
| EV | EV^C | AC | AC^C | PV | PV^C | SPI | SPI^C | CPI | CPI^C |
| April | 8 |
| 10 |
| 7 |
|
|
|
|
|
| May
| 17 |
| 18 |
| 16 |
|
|
|
|
|
| June | 25 |
| 27 |
| 23 |
|
|
|
|
|
| July | 15 |
| 18 |
| 15 |
|
|
|
|
|
| August | 7 |
| 9 |
| 8 |
|
|
|
|
|