Question: You have collected EV, AC, and PV data from your project for a five-month period. Complete the table. Calculate SPIC and CPIC. Compare the cost

You have collected EV, AC, and PV data from your project for a five-month period. Complete the table. Calculate SPIC and CPIC. Compare the cost and schedule performance for the project on a month-by-month basis and cumulatively. How would you assess the performance of the project? (All values are in thousands $.)
You have collected EV, AC, and PV data from your

EV EVCAC ACC PV PVC SPI SPIC CPI CPIC Apri8 May 17 June 25 July15 August7 10 18 27 18 16 23 15

Step by Step Solution

3.41 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

EV EV C AC AC C PV PV C SPI SPI C CPI CPI C April 8 8 10 10 7 7 11... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

663-B-M-L-P-M (2212).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!