Question: You have collected EV, AC, and PV data from your project for a five-month period. Complete the table. Calculate SPIC and CPIC. Compare the cost
.png)
EV EVCAC ACC PV PVC SPI SPIC CPI CPIC Apri8 May 17 June 25 July15 August7 10 18 27 18 16 23 15
Step by Step Solution
3.41 Rating (164 Votes )
There are 3 Steps involved in it
EV EV C AC AC C PV PV C SPI SPI C CPI CPI C April 8 8 10 10 7 7 11... View full answer