Question: You have collected EV, AC, and PV data from your project for a five-month period. Complete the table. Calculate SPIC and CPIC. Compare the cost
You have collected EV, AC, and PV data from your project for a five-month period. Complete the table. Calculate SPIC and CPIC. Compare the cost and schedule performance for the project on a month-by-month basis and cumulatively. How would you assess the performance of the project? (All values are in thousands $.)
.png)
Step by Step Solution
There are 3 Steps involved in it
EV EV C AC AC C PV PV C SPI SPI C CPI CPI C April 8 8 10 10 7 7 1... View full answer