Question: You have just performed a Single Time Estimate CPM analysis and have found that there is no path through the project network with zero slack

You have just performed a Single Time Estimate CPM analysis and have found that there is no path through the project network with zero slack values. What can you conclude?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!