Question: You have just performed a Single Time Estimate CPM analysis and have found that there is no path through the project network with zero slack
You have just performed a Single Time Estimate CPM analysis and have found that there is no path through the project network with zero slack values. What can you conclude?
You have multiple critical paths
The project will not be completed by the desired time
You have incorrectly performed the analysis
Only one path is optimal
More than one path is optimal