Question: You have just performed a Single Time Estimate CPM analysis and have found that there is no path through the project network with zero slack

You have just performed a Single Time Estimate CPM analysis and have found that there is no path through the project network with zero slack values. What can you conclude?

You have multiple critical paths

The project will not be completed by the desired time

You have incorrectly performed the analysis

Only one path is optimal

More than one path is optimal