Question: You receive bids from companies A , B , C , D and E . Contractor B does not meet the requirements of one of

You receive bids from companies A, B, C, D and E. Contractor B does not meet
the requirements of one of your qualification evaluation criteria & Contractor D
does not meet the requirements of one of your critical evaluation criteria
7. Please state which evaluation factors they did not meet and what you must
now do with these bids
Apply the following weights to your three differentiation evaluation factors
Bid differentiation evaluation factor 45%
Bidder differentiation evaluation factor 35%
Bidder differentiation evaluation factor 20%
The following is required (cont):
Score the 3 remaining contractors (A, C & E) as follows:
For bid differentiation evaluation factor 1, Contractor A must receive a score of
either 1,2 or 3. Contractor C, a score of 7 & Contractor E a score of either 8,9 or
10.
For bidder differentiation evaluation factor 2, Contractor A must receive a score of
either 4,5 or 6. Contractor C, a score of 10 & Contractor E a score of either 1,2 or
3.
For bidder differentiation evaluation factor 3, Contractor A must receive a score of
either 5,6 or 7. Contractor C, a score of 2 & Contractor E a score of either 8,9 or
10.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!