Question: You will perform material requirements planning given the following inputs for Week 7. Only do planning for P1 and S2 (and everything in the subassembly)

You will perform material requirements planning given the following inputs for Week 7. Only do planning for P1 and S2 (and everything in the subassembly) but taken into account the total usage of C2 in P1.

Master Production Schedule:

Week

Model

1

2

3

4

5

6

7

8

9

10

P1

10

30

20

Item Masters:

Item Number

Description

Item Type

UOM

Lead Time (wk)

Make/Buy

P1

Product 1

Model

each

1

Make

S1

Subassembly 1

Assembly

each

1

Make

S2

Subassembly 2

Assembly

each

1

Make

C1

Component 1

Part

each

1

Make

C2

Component 2

Part

each

1

Buy

C3

Component 3

Part

each

1

Make

M1

Material 1

Material

lb

1

Buy

M2

Material 2

Material

lb

2

Buy

Bill of Material:

Item Number

Description

Qty

P1

Product 1

1

S1

Subassembly 1

1

C1

Component 1

1

M1

Material 1

2.5

C2

Component 2

4

S2

Subassembly 2

2

C3

Component 3

1

M2

Material 2

1.5

C2

Component 2

2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!