Question: You will perform material requirements planning given the following inputs for Week 7. Only do planning for P1 and S2 (and everything in the subassembly)
You will perform material requirements planning given the following inputs for Week 7. Only do planning for P1 and S2 (and everything in the subassembly) but taken into account the total usage of C2 in P1.
Master Production Schedule:
|
| Week | |||||||||
| Model | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| P1 |
|
|
|
| 10 | 30 | 20 |
|
|
|
Item Masters:
| Item Number | Description | Item Type | UOM | Lead Time (wk) | Make/Buy |
| P1 | Product 1 | Model | each | 1 | Make |
| S1 | Subassembly 1 | Assembly | each | 1 | Make |
| S2 | Subassembly 2 | Assembly | each | 1 | Make |
| C1 | Component 1 | Part | each | 1 | Make |
| C2 | Component 2 | Part | each | 1 | Buy |
| C3 | Component 3 | Part | each | 1 | Make |
| M1 | Material 1 | Material | lb | 1 | Buy |
| M2 | Material 2 | Material | lb | 2 | Buy |
Bill of Material:
| Item Number | Description | Qty |
| P1 | Product 1 | 1 |
| S1 | Subassembly 1 | 1 |
| C1 | Component 1 | 1 |
| M1 | Material 1 | 2.5 |
| C2 | Component 2 | 4 |
| S2 | Subassembly 2 | 2 |
| C3 | Component 3 | 1 |
| M2 | Material 2 | 1.5 |
| C2 | Component 2 | 2 |