Question: Your project team has been tasked with assembling 100 data acquisition systems in 8 days. The estimated cost of each unit is $10,000, for a

Your project team has been tasked with assembling 100 data acquisition systems in 8 days. The estimated cost of each unit is $10,000, for a total project cost of $1,000,000. The following table provides the schedule and cost estimates determined at the start of the project:

We will evaluate the performance at the end of Day 4. The last two rows were added at the end of Day 4.

What is the budgeted cost of work performed (BCWP)?Your project team has been tasked with assembling

Day 2 Day 3 Day 4 18 Day 5 15 Day 6 15 Day 7 Day 8 5 12 15 10 120,000 150,000 180,000 150,000 150,000 100,000 5000 Day 1 Planned 10 number of built systems Estimated 100,000 cost for the day ($) Estimated 100,000 cumulative cost ($) Actual cost 80,000 for the day ($) Actual 80,000 cumulative cost ($) 220,000 370,000 550,000 700,000 850,000 950,000 100,000 100,000 160,000 160,000 180,000 340,000 500,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!