Question: Your Turn ( 2 ) table [ [ Activity , Predecessor,Optimistic,Normal,Pessimistic ] , [ A , - , 2 , 4 , 6 ]

Your Turn (2)
\table[[Activity,Predecessor,Optimistic,Normal,Pessimistic],[A,-,2,4,6],[B,-,3,5,9],[C,A,4,5,7],[D,A,4,6,10],[E,B C,4,5,7],[F,D,3,4,8],[G,E,3,5,8]]
Construct the AOA network diagram.
Identify the critical path. How long it will take to complete the project?
Find the probability that the critical path will be completed in 21 weeks or less. Base your calculations on (a)99.7%,(b)95% and (c)90% confidence intervals.
What should the project duration (D) be if we want a probability of 95%
 Your Turn (2) \table[[Activity,Predecessor,Optimistic,Normal,Pessimistic],[A,-,2,4,6],[B,-,3,5,9],[C,A,4,5,7],[D,A,4,6,10],[E,B C,4,5,7],[F,D,3,4,8],[G,E,3,5,8]] Construct the AOA network diagram. Identify

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!