Question: What is the output of the plan scope management process? a) The project charter b) Scope management plan and project charter c) Scope management plan
What is the output of the plan scope management process?
a) The project charter
b) Scope management plan and project charter
c) Scope management plan and requirement management plan
d) Requirement management plan and requirement management matrix