Question: You're managing the same project cited in question 34 using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000.

You're managing the same project cited in question 34 using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual value (AV) is $150,000. What is the schedule variance (SV) for the project? A. 100,000 B. �100,000 C. 50,000 D. �50,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!