Question: You're managing the same project cited in question 34 using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000.
You're managing the same project cited in question 34 using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual value (AV) is $150,000. What is the schedule variance (SV) for the project? A. 100,000 B. �100,000 C. 50,000 D. �50,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
