Question: You're managing the same project cited in question 3 4 using the earned value technique ( EVT ) for cost management. The project planned value

You're managing the same project cited in question 34 using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual value (AV) is $150,000. What is the schedule variance (SV) for the project?