Question: =+e. (**) After constructing the project network diagram, management comes up with the following information regarding how many days certain activities can be crashed and

=+e. (**) After constructing the project network diagram, management comes up with the following information regarding how many days certain activities can be crashed and at what cost:

ACTIVITY NUMBER OF DAYS ACTIVITY CAN BE CRASHED CRASH COST PER DAY C 3 $1,000 D 3 $2,500 E 2 $5,000 G 1 $1,000 H 3 $3,000 J 2 $2,000 M14_BOZA1581_05_GE_C14.indd 468 24/01/19 9:49 AM CHAPTER 14 ● Managing Projects 469