Question: Repeat Problem 12.14 if (mathrm{LFC}) is employed in area 2 alone. The area 2 frequency bias coefficient is set at (mathrm{B}_{f 2}=beta_{2}=600 mathrm{MW} / mathrm{Hz}).
Repeat Problem 12.14 if \(\mathrm{LFC}\) is employed in area 2 alone. The area 2 frequency bias coefficient is set at \(\mathrm{B}_{f 2}=\beta_{2}=600 \mathrm{MW} / \mathrm{Hz}\). Assume that LFC in area 1 is inoperative due to a computer failure.
Problem 12.14
A \(60-\mathrm{Hz}\) power system consists of two interconnected areas. Area 1 has \(1200 \mathrm{MW}\) of generation and an area frequency response characteristic \(\beta_{1}=400 \mathrm{MW} / \mathrm{Hz}\). Area 2 has \(1800 \mathrm{MW}\) of generation and \(\beta_{2}=\) \(600 \mathrm{MW} / \mathrm{Hz}\). Each area is initially operating at one-half its total generation, at \(\Delta p_{\text {tiel }}=\Delta p_{\text {tie } 2}=0\) and at \(60 \mathrm{~Hz}\), when the load in area 1 suddenly increases by 400 MW. Determine the steady-state frequency error and the steady-state tie-line error \(\Delta p_{\text {tie }}\) of each area. Assume that the reference power settings of all turbine-governors are fixed. That is, LFC is not employed in any area. Neglect losses and the dependence of load on frequency.
Step by Step Solution
3.28 Rating (151 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts