Question: Rework Problems 12.15 through 12.16 when the load in area 2 suddenly decreases by (300 mathrm{MW}). The load in area 1 does not change. Problem
Rework Problems 12.15 through 12.16 when the load in area 2 suddenly decreases by \(300 \mathrm{MW}\). The load in area 1 does not change.
Problem 12.15
Repeat Problem 12.14 if \(\mathrm{LFC}\) is employed in area 2 alone. The area 2 frequency bias coefficient is set at \(\mathrm{B}_{f 2}=\beta_{2}=600 \mathrm{MW} / \mathrm{Hz}\). Assume that LFC in area 1 is inoperative due to a computer failure.
Problem 12.16
Repeat Problem 12.14 if \(\mathrm{LFC}\) is employed in both areas. The frequency bias coefficients are \(\mathrm{B}_{f 1}=\beta_{1}=400 \mathrm{MW} / \mathrm{Hz}\) and \(\mathrm{B}_{f 2}=\beta_{2}=600 \mathrm{MW} / \mathrm{Hz}\).
Step by Step Solution
3.29 Rating (152 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts