Question: For the network shown: a. Determine the critical path and the early completion time in weeks for the project. b. For the data shown, reduce
For the network shown:
.png)
a. Determine the critical path and the early completion time in weeks for the project.
b. For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at yourschedule.
3875679 3775633 7254367 l, 508 6744 ABCDEFG
Step by Step Solution
3.32 Rating (158 Votes )
There are 3 Steps involved in it
a ABDG 5 10 6 4 25 weeks b Activity Normal Time NT Normal Cost NC Crash Time C... View full answer