Question: The optimistic, most likely, and pessimistic times for the tasks comprising a project are as follows. Use the data to compute the expected completion time
.png)
Task 3 813 5 11 16 9 1924 11832 4 10 12
Step by Step Solution
3.32 Rating (173 Votes )
There are 3 Steps involved in it
Using equations 121 and 122 we can calculate both the expected completion ti... View full answer