Question: The optimistic, most likely, and pessimistic times for the tasks comprising a project are as follows. Use the data to compute the expected completion time
The optimistic, most likely, and pessimistic times for the tasks comprising a project are as follows. Use the data to compute the expected completion time and variance for each task.