Question: The project start-up phase is complete, and you are now ready to finalize the operational plan. Below are six steps that are often part of
1. Draw diagrams for each individual WBS element.
2. Establish the work breakdown structure and identify the reporting elements and levels.
3. Create a coarse (arrow-diagram) network and decide on the WBS.
4. Refine the diagram by combining all logic into one plan. Then decide on the work assignments.
5. If necessary, try to condense the diagram as much as possible without losing clarity.
6. Integrate diagrams at each level until only one exists. Then begin integration into higher WBS levels until the desired plan is achieved.
Step by Step Solution
3.48 Rating (165 Votes )
There are 3 Steps involved in it
Correct order is 3 Create a coarse arrowdiagram network and decide on the WBS 2 Establish the wor... View full answer