Question: The scheduler at Haley's Airframes uses MPS time-phased records for planning end item production. The planner is currently working on a schedule for a strut
The scheduler at Haley's Airframes uses MPS time-phased records for planning end item production. The planner is currently working on a schedule for a strut assembly, one of Haley's top-selling spare parts. The planner uses a production lot size of 170 and a safety stock of 15 for the strut assembly.

a. Complete the MPS time-phased record for product P24.
b. Can the planner accept the following orders? Update the MPS time-phased record for accepted orders.

WEEK 4 5 2 3 ITEM: P24 140 130 45 130 18 145 145 130 140 140 Forecast Orders Available Available to promise MPS 38
Step by Step Solution
3.22 Rating (171 Votes )
There are 3 Steps involved in it
a Assumptions Lead time 0 days Onhand 120 units Data lot size of 170 and a safety stock o... View full answer