Question: The scheduler at Haley's Airframes uses MPS time-phased records for planning end item production. The planner is currently working on a schedule for a strut

The scheduler at Haley's Airframes uses MPS time-phased records for planning end item production. The planner is currently working on a schedule for a strut assembly, one of Haley's top-selling spare parts. The planner uses a production lot size of 170 and a safety stock of 15 for the strut assembly.

WEEK 4 5 2 3 ITEM: P24 140 130 45 130 18 145 145 130 140 140 Forecast Orders Available Available to promise MPS 38

a. Complete the MPS time-phased record for product P24.

b. Can the planner accept the following orders? Update the MPS time-phased record for accepted orders.

The scheduler at Haley's Airframes uses MPS time-phased records for

WEEK 4 5 2 3 ITEM: P24 140 130 45 130 18 145 145 130 140 140 Forecast Orders Available Available to promise MPS 38

Step by Step Solution

3.22 Rating (171 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Assumptions Lead time 0 days Onhand 120 units Data lot size of 170 and a safety stock o... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

852-B-M-L-S-C-M (4404).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!