Question: Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash
Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the adjusted totalcost.
.png)
Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 100 150 100 60 70 90 150 Initial project duration 12 1X Total direct cost $ 4
Step by Step Solution
3.53 Rating (167 Votes )
There are 3 Steps involved in it
Activity Normal Narmal Maximum Time Cost Crash Time 100 150 200 200 A B DE... View full answer