Question: Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash

Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the adjusted totalcost.

Use the information contained below to compress one time unit

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 100 150 100 60 70 90 150 Initial project duration 12 1X Total direct cost $ 4

Step by Step Solution

3.53 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Activity Normal Narmal Maximum Time Cost Crash Time 100 150 200 200 A B DE... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

177-B-M-L-P-M (1416).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!