Using the following project information The critical path is A-C-E-G-I-J. Calculate the probability that the project will
Question:
The critical path is A-C-E-G-I-J.
Calculate the probability that the project will be completed in 38 weeks.
Calculate the probability that the project will be completed in 42 weeks.
Transcribed Image Text:
Optimistic Time Estimate(weeks) Variance Expected Activity Most Pessimistic Immediate Likely Predecessor(s) Time Time Time Estimates (weeks) Estimates (weeks) (weeks) 1.000 6.00 none A 0.444 5.00 7.33 12 A 1.778 7.67 10 1.000 10.17 5 10 16 3.361 D,E 0.111 4.00 0.694 G 8. D,E 5.83 Н 10 0.694 6.33 11 1.000 8.00 3.00 3 3 Н. 0.000 6. 3. 3. 3.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 54% (11 reviews)
Path Expected Completion Time Variance 38 week zvalue ...View the full answer
Answered By
Abigael martinez
I have been a tutor for over 3 years and have had the opportunity to work with students of all ages and backgrounds. I have a strong belief that all students have the ability to learn and succeed if given the right tools and support. I am patient and adaptable, and I take the time to get to know each student's individual learning style in order to best support their needs. I am confident in my ability to help students improve their grades and reach their academic goals.
5.00+
1+ Reviews
10+ Question Solved
Related Book For
Methods of IT Project Management
ISBN: 978-1557536631
2nd edition
Authors: Jeffrey Brewer, Kevin Dittman
Question Posted:
Students also viewed these Managerial Accounting questions
-
Using the following project information The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be completed in 38 weeks. P(project 38) = (b) Calculate the probability...
-
Using the follow gin project information The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be completed in 38 weeks. (b) Calculate the probability that the project...
-
Using the following project information, calculate the variance for each of the project activities. Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Estimate (weeks) Estimates...
-
How to find the expected utility of profit under each alternative crop Table 1. Annual Returns to Cropping Alternatives ($ profit / acre) Outcome Worst Bad OK Good Great Probability 0.1 0.2 0.4 0.2...
-
A continuous cable of total length l is wrapped around the small pulleys at A, B, C, and D. If each spring is stretched a distance b, determine the mass M of each block. Neglect the weight of the...
-
A 3.00-m-long, 240-N, uniform rod at the zoo is held in a horizontal position by two ropes at its ends (Fig. 11.30). The left rope makes an angle of 150° with the rod and the right rope makes an...
-
Water is to be used to absorb acetone from a dilute mixture with air in a tower packed with 3.5-in. metal Pall rings. Average conditions in the tower are: \[\text { Temperature }=25^{\circ}...
-
Assume that you recently graduated with a major in finance and just landed a job in the trust department of a large regional bank. Your first assignment is to invest $100,000 from an estate for which...
-
1. The fighters of the Ultimate Fighting Championship (UFC) filed suit against the UFC, alleging that the UFC unlawfully monopolized the output and input markets in mixed martial arts. In particular,...
-
2 3 4 On the SalesData worksheet in cell B4, use an XLOOKUP function to retrieve the product name for the ProductID in cell A4, using the table of data about the products at Kelly Computers on the...
-
Oakley Company does not ring up sales taxes separately on the cash register. Total receipts for February amounted to $42,800. If the sales tax rate is 7%, what amount must be remitted to the state...
-
1. Activity based costing for selling and administrative expenses can also be beneficial in allocating expenses to various products. Which of the following is the best allocation base for help desk...
-
(a) What are the two most critical fields in the digital certificate? (b) What field in a digital certificate allows the receiver of a certificate to determine if the certificate has been altered?...
-
Write a brief evaluation of the following secondary information sources: A well-known popular daily financial newspaper A well-recognized global market research organization with a reputation for...
-
The anniversary date of the founding of the first store in the chain where you work as marketing manager is coming up. Across the globe, the chain has 186 stores with just over 322,000 customer...
-
You appreciate how important phones are to your companys operations, but the amount of conversational chatter in your work area has gotten so bad that its hard to concentrate on your work. You...
-
Why is it important to be conscious of the listening style you are using during any phase of a conversation or presentation?
-
Now that youve explored routine, positive, negative, and persuasive messages, review the following message scenarios and identify which of the four message strategies would be most appropriate for...
-
Are China and India converging to a neo-liberal model of capitalism or do they reinforce the diversity of capitalism? What factors would prevent a convergence of employment practices in Asia?
-
A new car sold for $31,000. If the vehicle loses 15% of its value each year, how much will it be worth after 10 years?
-
The concentration of an active ingredient in the output of a chemical reaction is strongly influenced by the catalyst that is used in the reaction. It is felt that when catalyst A is used the...
-
From the information in Review Exercise 8.70 compute (assuming B = 65%) P(XB > 70).
-
Given a normal random variable X with mean 20 and variance 9, and a random sample of size n taken from the distribution, what sample size n is necessary in order that P(19.9 < X < 20.1) = 0.95?
-
Assume you have a portfolio consisting of a $400,000 investment in stock A and a $600,000 investment in stock B. Suppose that the daily volatilities of these two assets are 2% and 1.5%, respectively,...
-
What is the role of education in promoting social mobility and reducing inequality, and how can educational systems be reformed to better serve diverse populations while preparing individuals for the...
-
A European call option and put option on a non-dividend paying stock both have a strike price of $51 and an expiration date in 6 months. The put sells for $2.50 and the call sells for $2. The...
Study smarter with the SolutionInn App