Using the following project information The critical path is A-C-E-G-I-J. Calculate the probability that the project will

Question:

Using the following project information
Optimistic Time Estimate(weeks) Variance Expected Activity Most Pessimistic Immediate Likely Predecessor(s) Time Time Ti

The critical path is A-C-E-G-I-J.
Calculate the probability that the project will be completed in 38 weeks.
Calculate the probability that the project will be completed in 42 weeks.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Methods of IT Project Management

ISBN: 978-1557536631

2nd edition

Authors: Jeffrey Brewer, Kevin Dittman

Question Posted: