Question: Using the information from the following table, create an AON network activity diagram: a. Calculate each activity TE (rounding to the nearest integer), b. the
Using the information from the following table, create an AON network activity diagram:
a. Calculate each activity TE (rounding to the nearest integer),
b. the total duration of the project,
c. its early start, early finish, late start, and late finish times, and the slack for each activity (Use TE values)
d. Finally, show the projects critical path.

Preceding Activities Activity Best Likely Worst A 12 15 25 B A 4 6 11 12 12 30 D 8 15 20 B, C A E 7 12 15 F E 9 9 U OWO I - - 42 19 G 13 17 D, E F H 5 10 15 G 11 13 20 2 3 6 G H J,1 K 8 12 22