Question: Using your results from Problem 6, (a) Calculate the probability that the project will be completed in 38 weeks. (b) Calculate the probability that the
Using your results from Problem 6,
(a) Calculate the probability that the project will be completed in 38 weeks.
(b) Calculate the probability that the project will be completed in 42weeks.
.png)
Most Optimistic Likely Pessimistic Time Time Time Estimate Estimates Estimates Immediate Activity (weeks (weeks) (eks) Predecessor(s one 12 16 10 4 D, E D, E 10 H, I
Step by Step Solution
3.35 Rating (167 Votes )
There are 3 Steps involved in it
a Pproject 38 Pcritical p... View full answer