Question: Using the information on the student data set for Problem input the data into MS Project. Display and print the schedule in Gantt chart format
.png)
0 |Task Name |Duration -Start Finish Predecessors 7 days 1/9/2011 1/27/20112 2 days1/17/201 1/18/2011 3 days /28/20 /1/1 5 days /28/20 2/3/201 1 7 days 1/9/201 1/27/2011 2 3 days 2/2/2011 2/4/20113 4 days 2/4/2011 /9/2014 6 days 2/7/2011 /14/201 ,6 5 days 2/15/2011 2/21/201 7,8
Step by Step Solution
3.35 Rating (164 Votes )
There are 3 Steps involved in it
Gantt Chart 1 2 3 4 5 6 7 8 9 B 3 Task Name A Booww C D E F G H 1 Y Duration 17 days ... View full answer