Question: Using the information for Exercise 8.9, input the data into MS Project. Display and print the schedule in Gantt chart format, as shown in Exhibit
Using the information for Exercise 8.9, input the data into MS Project. Display and print the schedule in Gantt chart format, as shown in Exhibit 8.19.
Exercise 8.9
Given the information below, create the project schedule network. Then, using the enumeration method, calculate and show all of the paths through the network. Show how long each path will take. Identify the critical path. Show the schedule on a Gantt chart showing critical and non-critical activities and float.


Activity A B D E F G H I Days 7 2 3 5 7 3 4 6 5 Immediate Predecessor B A AB A C D E, F G, H