Question: Using the information on the student data set for Problem input the data into MS Project. Display and print the schedule in Gantt chart format
.png)
0 Task Name Duration -start Finish , Predecessors. A 5 days 1/17/2011 1/21/2011 2 days 1/24/201 /25/20 1 4 days 1/24/2011 1/27/2011 1 7 days 1/24/2011 2//2011 1 E 3 days 1/26/2011 1/28/2011 2 6 days 1/28/2011 2/4/2011 2,3 8 days 2/7/201 2/16/2011 5,6,4
Step by Step Solution
3.34 Rating (163 Votes )
There are 3 Steps involved in it
Gantt Chart 4 123 ABCDEFG 567 0 Task Name Duration 5 days 2 days 4 d... View full answer