Question: 1. Draw the network diagram for the project. 2. Compute the expected activity times and activity time variances for each task. 3. Identify the projects
2. Compute the expected activity times and activity time variances for each task.
3. Identify the project’s critical path.
4. For what project duration could Roberta be 90 percent certain of completing the layout redesign project?
5. Which tasks, if any, would you recommend crashing?
Step by Step Solution
3.49 Rating (162 Votes )
There are 3 Steps involved in it
1 2 Activity Description Activity Label Predecessor Optimistic Time days Most Likely Time days Pessi... View full answer