Question: A job was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95 percent, and workday allowance
A job was timed for 60 cycles. It took an average of 1.2 minutes per cycle. The performance rating was 95 percent, and workday allowance is 10 percent. Determine each of the following:
a. Observed time.
b. Normal time.
c. Standard time.
Step by Step Solution
3.26 Rating (178 Votes )
There are 3 Steps involved in it
OT 12 minutes PR 95 A 10 of work da... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
686-B-M-L-O-M (4834).docx
120 KBs Word File