Question: 12) A project network is shown below. Use a forward and a backward pass to determine the critical path, and (25pts) then fill out the


12) A project network is shown below. Use a forward and a backward pass to determine the critical path, and (25pts) then fill out the table below. Activity times are in weeks. Staat Finish Precedence Actvities Activity Time (weeks) Critical Path? Activity ESLS EFLF Slack Activity Precedence Activities Activity Time (weeks) E L SEF LF Slack Critical Path? I Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%? Previous 1 | 2 3 | 4 316 Next