Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.

A project network is shown below. Use a forward

A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. A 3 D 4 Finish Start B 4 | Ho E 12 5 8 F 10 Activity Critical Precedence Activities Path? Activity Time (weeks) ES LS EF LF Slack A B C D E F G H 1 Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in more than 28 weeks more or less than 50%