A work-study sample of a manufacturing activity conducted over a 40-hour period shows that a worker with

Question:

A work-study sample of a manufacturing activity conducted over a 40-hour period shows that a worker with an 85% rating produced 12 parts. The worker's idle time was 10% and the allowance factor was 12%
Find the Normal and Standard time for this activity.