Question: (a) A work-study sample of a manufacturing activity conducted over a 40-hour period shows that a worker with an 85% rating produced 12 parts. The

(a) A work-study sample of a manufacturing activity conducted over a 40-hour period shows that a worker with an 85% rating produced 12 parts. The worker's idle time was 10% and the allowance factor was 12%. Find the Normal and Standard time (based on job) for this activity. What is the standard time per part