Question: Balance the assembly line in Exhibit 8.13 for (a) A shift output of 40 pieces and (b) A shift output of 20 pieces. Assume an
Balance the assembly line in Exhibit 8.13 for
(a) A shift output of 40 pieces and
(b) A shift output of 20 pieces. Assume an eight-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case.
.png)
Exhibit 8.13 Precedence Diagram for Problem 13 Time 6 6 5 4
Step by Step Solution
★★★★★
3.30 Rating (162 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
For a shift output of 40 pieces cycle time C 86040 12 minutesunit Work Station Tasks Total Time Idle ... View full answer