Question: Reconfigure the Gantt chart in problem 2 to include some different predecessor relationships. Optional: Solve this problem with Microsoft Project. a. Assume that activities B

Reconfigure the Gantt chart in problem 2 to include some different predecessor relationships. Optional: Solve this problem with Microsoft Project.
a. Assume that activities B and C are linked with a “finish to finish” relationship. Does that change the expected completion date for the project?
b. For activity F, add a lag of three days to its predecessor relationship with activity D. By adding the 3-day lag to F, what is the new expected duration for the project?
c. Suppose you now added a start to start relationship between activities F and G to the new Gantt chart. How does this additional relationship change the expected completion date for the project?

Step by Step Solution

3.34 Rating (172 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a No linking B and C in a finish to finish relationship will not affect the critical path be... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

663-B-M-L-P-M (2136).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!

Q:

-2